Friday, 9 April 2010
Carpenters at work
We have had some few rainy days that have delayed it all, but we are now back at it. Here in the photo today, the carpenters are finishing the wood at one side of the swimming pool. As you can see, there is a lot of wood. This side should be completed by tuesday, excepting some details like the showers, that are to be done at the end of the month.
Tuesday, 30 March 2010
Tiles and more tiles
Inside the adults swimming pool, the tiles will be finished in about one week. Now it looks very bad because of all the empty boxes, but this should be soon arranged. From then on, we will put the lights, water entrances and drains.
Saturday, 27 March 2010
New brochure
A new version of our brochure is available, both at the reception and here in the contact/info page.
Friday, 19 March 2010
New map
The new map of the camping is already available in this site. It contains the final shape of the new swimming pool and the area all around. As you can see, there have been some changes from the initial project that we showed in December 2009.
Thursday, 18 March 2010
A first impression
Here you can get a first impression of how the children's swimming pool is going to look. We are finishing the tiles inside the pool, while starting to prepare the terrace all around. Still a lot to do, but we are on track for the 1 May.
Wednesday, 17 March 2010
Sunday, 28 February 2010
Progress at the machine room
The machine room is progressing well. As you can see there is still quite a chaos, we have had several days with heavy rain and the room is still without roof, in order to allow the easy transport of the machinery. We plan to finally put the roof in two weeks.
Wednesday, 24 February 2010
New connection boxes
The camping plots beside the swimming pool area have been modified because of the new slopes that are now needed. This has obliged us to remove the old boxes for water and electricity, and thus it was the occasion to try a new type of 'box' for that equipment, we name it box 4.0, our fourth version. We think it follows the EU guidances for electrical equipment. You can see that there are the new EU electricity connectors, the typical water connectors, it misses a water drain just below them, but at a few centimeters distance there are two water drains for connections from the caravans.
In the next days we will put what is missing: a fence and a line of bushes to separate these plots from the swimming pool area. Afterwards we will try that grass grows everywhere.
In the next days we will put what is missing: a fence and a line of bushes to separate these plots from the swimming pool area. Afterwards we will try that grass grows everywhere.
Friday, 19 February 2010
Filling with concrete in children's pool
Here finishing the concrete around the children's swimming pool. You can see that it is going to be about 40 cm deep. In a couple of days we will begin putting the tiles inside that small pool.
Tuesday, 2 February 2010
Putting pieces together
Meanwhile there is also a lot of work to be done in the new machine room. Antonio and Salvador are here trying to figure out what to do with all the pieces. You can see some of the big filters that are needed to clean the water.