Friday 31 May 2013

Small portion mostly finished

The building up of that small portion is now finished, a lot of details need to be addressed but the critical part is done. As you can see here the nets are in the right color.

Thursday 30 May 2013

Black disaster

The builders of the new playground have now discovered that the nets have arrived in black color, when we all wanted white. So, they are going to have to mount them first in black and in some months they will have to replace all the nets in the right color... It will be no small task because as you will see there will be a lot of nets.

Monday 27 May 2013

Now comes the laundry

A new, big ironing machine is arriving. This last months we have modified a little bit more upstairs from the Amberes building, so we have more space for our internal laundry. This new machine goes now to the new space. Still to be decided, but for 2014 we would like, in the bungalows and apartments, to provide always the bed clothes and towels.

Saturday 25 May 2013

And material arriving

New material is arriving for the new playground, basically wood poles. Some drainage work is already done, much more still to do.

Thursday 23 May 2013

Progress in that small portion

We have had some rain, the work progresses slower but it still continues. In two days the basic build up of that small portion of the playground will be finished.

Tuesday 21 May 2013

Building a small portion of the game

There is a small portion that the builders are right now already mounting. This portion is rather independent of the rest and the material already arrived.

Sunday 19 May 2013

New signs inside the supermarket, changes coming

This summer we are trying to sell more prepared meals in the supermarket, and thus we have added new big signs to publizice that food.
Since last summer we have changed the name in the entrance of that building, from 'Supermarket' to 'Commercial Center', and while the supermarket area is remaining, the objective goes more and more towards the bread and prepared meals section.

Friday 17 May 2013

Water draining in the new playground area

Now the builders are beginning to prepare the terrain in order to drain the water from the rain, so it goes to the river nearby. Because the area is rather big this work will take a lot of time.

Wednesday 15 May 2013

Progress in playground installation

Installation of the playground is progressing well but it is a slow and long process, at least 20 more days until the basic build up is finished, and afterwards there will be some other aspects to finish. We expect the playground to be usable in about one month, so by the middle of June, always if the weather permits that continuous progress.

Saturday 11 May 2013

Plants for the new playground area

The new playground area is needing a lot of plants and the gardeners are busy preparing the terrain and putting them. We are going to need about one month still until the area will be ready for the clients.

Wednesday 8 May 2013

The beginning of the build up

Finally after months waiting, the building up of the games in the playground area has begun. Let's hope there is no raining... and then it should be finished in about one month.

Tuesday 7 May 2013

More progress in the ping pong area

JuanMa is preparing the ground around the ping pong tables to put some grass. Meanwhile, people can already play ping pong in the 4 tables.

Thursday 2 May 2013

Planting bushes near the multisport court

The gardeners are now planting a line of bushes near the multisport court. In the next days the surroundings of that area will receive some more plants in order to make it greener.
Behind the gardeners you can already see some children playing in the new court.