Thursday 31 May 2012

Progress in the terrace

The terrace floor, walls and railings are progressing well, if the weather continues like now, sunny and dry, it could be finished in one week. After that there will still remain some details near the windows. It all takes longer but the general aspect is beautiful.

Friday 25 May 2012

Door to the bathroom

Here the smiths are preparing one of the bathroom's doors. It looks shiny and it will be, we are trying to put a touch of modern design.

Tuesday 22 May 2012

Lamps in the stairs

The stairs leading up to the new lounge bar are being finished, now installing two big lamps. A special provisional structure is needed because of height and safety considerations. Lastly we are now realizing that the cables of the lamps will need a rigid support because there is sometimes a stream of air that otherwise moves them.

Thursday 17 May 2012

Improvements on the entrance signs

In the process of changing the camping's name we also needed to change the sign in front of the bridge. Here is the new sign, we have also repainted the sliding maintenance door, and somewhat repainted and improved the fence. This new look should last for the next few years.

Tuesday 15 May 2012

Terrace already shows some floor

As the carpenters put more and more pieces, the terrace is beginning to show the floor in its final shape. Still, the work in the terrace will last probably two more weeks, because of the walls and the long railing. There are now 3 carpenters in the project.

Friday 4 May 2012

Still another door, now to the terrace

The main door to the terrace is going to be rather wide and open automatically. Here there is a carpenter looking that the wood floor adjusts to the door. You can also see that there is the base of a ramp that leads from inside to that door. This will allow wheelchair users to go to the terrace.