Saturday, 19 April 2008
Our new petanque area
After the roads and new plots, now it is time to finish the petanque areas. Here painting and fixing the big pieces of wood.
Friday, 11 April 2008
Internet cafe, new opening
We will open the internet cafe on 1st May, with the following prices:
- Computer, aprox. 20 minutes: 1 €
- WiFi, aprox. 1 hour (continuous): 2 €
- WiFi, aprox. 2 hours (continuous): 3 €
- WiFi, aprox. 24 hours (continuous): 10 €
Saturday, 29 March 2008
2008 season opening
We open again, the new season 2008 begins. We will close on 15 October. Here is the new look of the entrance, with new colors and pictures.
Sunday, 23 March 2008
Higher temperatures soon
Fortunately we are going to open on 29 March, and not now. A cold wind (tramontana) is currently blowing and has exceptionally lowered the temperatures during these last days. The weather should again change tomorrow, so temperatures will be much higher on next weekend.
Wednesday, 19 March 2008
Rebuilding street near reception
After passing some new drainage lines, the street near reception needs rebuilding. This street is used mainly by trucks that go to the supermarket.
Wednesday, 12 March 2008
Rebuilding street 7
Street 7 is almost finished, the machine is extending sand, afterwards the road needs to be leveled, compacted and some lights are still missing. The new boxes for water and electricity have been put and they are almost ready, more about them soon.
Thursday, 28 February 2008
Starting two new petanque areas
We are starting to prepare 2 petanque areas, between streets 8 and 9, near the supermarket. They are going to have the minimum size that is needed for international competitions, 15 x 4 meters, according to the catalan petanque association.
Friday, 15 February 2008
Finishing street 8
Street 8 is being finished, now putting the borders. On the right side, the new plots will be 120 m2 and the electrical and water connections will go to the south side. Because we will try to grow grass, these plots will surely not be available from the beginning, but later from 1st May.
Friday, 8 February 2008
Beginning transformation of street 7
Street 7 is being very much transformed, with new borders, slopes and electricity lines. Although it is looking terrible today, this area should be finished at the end of this month, three weeks from now. The resulting camping plots will be bigger and fully equipped.
Saturday, 12 January 2008
Putting some new pipes
The work in the camping plots is progressing, but a lot is still needed. Here below, some new electricity and water lines near streets 6 and 7.