Sunday 25 March 2012

Terrace progressing slowly

Work in the terrace is progressing slower than planned. While have had some rainy days, the delay is mostly due to the task taking much more effort than initially thought. Also, the carpenter will need much more days than planned. As a result, the opening day for the lounge bar will have to move to the beginning of June. Because this bar is a new offer in the campsite, this is not going to disrupt the normal functioning of the rest of the services.